TAMIMI GROUP

Tamimi Group was established in 1953, by the late founder Chairman. Sheikh Ali  A.Tamimi, to carry out Pipeline Construction, General Construction and related works.

ICC (PVT) LIMITED

It formerly known as Imperial Construction Company was established in 1931 and has contributed a vital and active role to achieve the objective of self sufficiency in electrical technology in Pakistan. Over the past 94 years.

ICC further expanded its business in the Kingdom of Saudi Arabia for the Construction of Substations, Transmission-Lines, Underground cables  works on Turnkey basis.

TAMIMI CO and ICC (PVT) LIMITED

Pakistan formed a new joint venture company namely Arabian Electrical Transmission Line Construction Co. Ltd (AETCON) in 1998 to undertake turnkey projects for the Construction of Transmission Lines, Substations & Electro Mechanical works in the Saudi Arabia

Arabian Electrical Transmission Line Construction Company LTD (AETCON)

It is one of the most consolidated and renowned company in the Kingdom of Saudi Arabia.The Company Specialized in Power Transmission, Distribution systems, Electrical and communication systems along with all associated Civil works including Design, Procurement of Material, Transportation,  Erection, Testing and Commissioning. With many Years of  international expertise we have established a name in business that is respected both by our clients and our suppliers. Our success is due to our ability to work effectively with our clients, as a trusted partner. Our experience of every aspects of our clients needs, allow us to meet their every cahllenge.

It is Registered & Pre-qualified as a Contractor with Saudi ARAMCO, SABIC, SAUDI railways (SRO) & Saudi Electric Company 33kV – 600kV (Overhead Transmission line) / 33kV – 132kV (Underground Works)   in the Kingdom of Saudi Arabia.

  • Company Registration No. 2050034036
  • Zakah Certificate No. 1110217292
  • Contractor Classification Certificate No 8471
  • Chamber of Commerce & Industry No 1774
  • Saudi Electric Co. 1000293
  • Saudi ARAMCO Registration No. 10007052
  • Saudi ARAMCO ECN Account No. ia070167
  • SABIC Contractor Registered
  • NEOM Registered

Over Head Transmission Lines

  • Heigher Voltage: We construct long distance transmission at heigher voltage steel tower, ensuring the uninterrupted flow of electricity across vast distances. Our focus lies in optimizing line design, minimizing losses, and enhancing overall system reliability.
  • Advanced Engineering: We leverage the latest advancements in engineering and technology, including:
    • Computer-aided design (CAD) software: For precise planning and design, minimizing environmental impact and optimizing line configurations.
    • PLS CAD Software: To analyze the plan and profile and to calculate the project material to ensure the long-term durability and efficeiency.
    • Tower Errection and Stringing Work: We specialized in construction of tower foundation, tower errection, conductor & OPGW stringing upto 525kV HVDC line.
    • OPGW Testing and Commisioning: We specialize in the process of verifying and ensuring the overhead ground wire to meet the specified design requirement and standard that are in proper working condition before being put into service.
  • Quality Control: We adhere to the highest quality standards throughout the entire construction process, from material selection and procurement to rigorous testing and commissioning.

Solar System

  • We specialize in the installation and maintenance of solar electricity to convert the energy from sun light into electricity by using photo voltaics or indirectly using concentrated solar power.
    Environmental Benefits:
  • Reduced Greenhouse Gas Emissions: This is arguably the most crucial benefit. Solar power produces electricity without burning fossil fuels, drastically reducing the emission of greenhouse gases like carbon dioxide, which are the primary drivers of climate change. This helps mitigate global warming and its associated consequences.

  • Improve Air Quality: Burning fossil fuels releases pollutants that contribute to smog, acid rain, and respiratory problems. Solar power is a clean energy source, reducing air pollution and improving public health

  • Conserve Water Reduced Water Consumption: Traditional power plants often require vast amounts of water for cooling. Solar power systems, especially photovoltaic (PV) systems, use very little water, conserving this precious resource.

  • Save on Your Power Bills: By implementing the solar system we can cut short our power bills which cause a major impact on runing any project and by installing battery with the your solar PV system, you can store your solar power not only used during the day but use at night time also. This should cut your electricity bills even further.

Underground Cables

  • Reliable and Efficient: We specialize in the installation and maintenance of high-voltage underground cables upto 132kV, including splicing, testing and comminsioning, for reliable and efficient power transmission in urban and sensitive areas.
  • Advanced Cable Technologies: We utilize the latest advancements in cable technology, including:
    • Cross Link Polyethylene (XLPE): Offering high dielectric strength and excellent performance commanly used for power transmission and distribution.
    • NFOC: Integrated for communication and monitoring purposes.
    • Advanced jointing and termination techniques: Ensuring seamless and reliable connections.
  • Comprehensive Services: Our services encompass:
    • Cable route planning and design.
    • Trenching and cable laying.
    • Jointing and termination.
    • Testing and commissioning.
    • Ongoing maintenance and fault location.
Copyright © 2012 – 2024. All Rights Reserved.